Preheating Of High-pressure Alloy Pipes Before Welding

Feb 19, 2024

16Mn High-pressure Alloy Pipes Supplier-GNEE

1. The necessity of preheating
Due to its high working pressure and usage requirements, high-pressure alloy pipes must be preheated before welding. Preheating can change the grain boundary structure of the pipe material, reduce the cooling rate during the welding process, thereby avoiding cracks and deformation during the welding process, while improving the welding quality and durability.
2. Preheating temperature
Preheating temperature is a critical parameter. If it is too low or too high, it will have a negative impact on the welding quality. It is generally believed that preheating at high temperatures will achieve the best results, while cracks and deformation will occur at low temperatures.
For different types of high-pressure alloy pipes, the preheating temperatures are also different. Generally speaking, carbon steel pipes need to be preheated at a temperature of 150°C - 250°C; while high strength low alloy and alloy steel pipes need to be preheated at a temperature of 250°C - 400°C. For stainless steel pipes, the preheating temperature is usually between 150°C - 200°C.

A335 alloy steel pipe

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


3. Keeping time
Holding time is also an important parameter. The holding time refers to the time the pipe needs to stay at the preheating temperature. Insufficient heat preservation time will not completely change the grain boundary structure, and excessive heat preservation will cause the pipe to be easily deformed.
Generally speaking, the holding time should be calculated based on the size and wall thickness of the pipe. Generally, the larger the diameter and thicker the wall thickness of the pipe, the longer the insulation time. Generally speaking, the holding time needs to be between 30 minutes and 1 hour.

alloy steel tube

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


4. Other matters needing attention
During the preheating process of high-pressure alloy pipes, the following issues also need to be paid attention to.
First, the pipes need to be cleaned and degreased. Impurities such as grease and welding slag on the surface of the pipeline will affect the preheating effect of the pipeline, so cleaning work should be done.
Secondly, the environment must be kept dry and stable during preheating and welding, especially under high temperature conditions. At the same time, ensure that the preheating area is not disturbed by external forces, such as wind, water, etc.
Finally, a suitable preheating method needs to be selected. At present, commonly used preheating methods mainly include flame welding, resistance heating, electric heating, etc. The selection of different methods needs to be based on specific circumstances.