Cold Drawing Process of Precision Seamless Steel Pipe

Nov 02, 2023

Cold Drawing Seamless Steel Pipe

Cold Drawing Process of Precision Seamless Steel Pipe

 

Cold-drawn precision seamless steel pipe has the characteristics of no oxide layer on the inner and outer walls, no leakage under high pressure, high precision, high smoothness, no deformation in cold bending, no cracks in expansion and flattening, and anti-rust treatment on the surface. Mainly used in mechanical structures. , hydraulic equipment and pneumatic or hydraulic components of automobiles and motorcycles, such as cylinders or oil cylinders.
10002

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The cold drawing process flow is: hot rolled tube blank -> tube blank inspection and polishing -> tube blank pickling -> tube blank re-inspection after pickling -> cold drawing -> straightening before fine drawing -> pickling, lubrication - >Precision drawing->finished product pre-processing->warehousing.

 Precision Seamless Steel Pipe

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Precautions During Manufacturing Process
1.tube blank
The wall thickness of the tube blank should be uniform and there should be few defects on the inner and outer surfaces; equipment should be equipped for outer surface polishing and inner hole defect cleaning.
2. Re-inspection
Compared with ordinary cold-drawn steel pipes, the production of cold-drawn precision seamless steel pipes adds pickling and re-inspection processes for hot-rolled capillary tubes. This is mainly to ensure that the outer surface of the capillary tubes is free of defects such as wrinkles and cracks, and to eliminate wrinkles and serious defects on the inner surface of the capillary tubes. Defects such as scratches and pitting.

3. Tools
Generally speaking, the surface finish of the tools used to produce cold-drawn precision seamless steel pipes is required to be above Ra0.4, the dimensional accuracy is required to be above H3, and the hardness is required to be above HRC70. At the same time, it is required that no plugging or steel sticking to the mold should occur during the drawing process.
4. Annealing
Annealing is a very important process in the production of all cold drawn tubes. The quality of annealing affects both the performance of the steel pipe and the removal of scale. Cold drawn precision steel pipes need to be equipped with non-oxidizing bright annealing furnace equipment.

5. Pickling
During the sulfuric acid pickling process, precision seamless steel pipes are prone to form "black slag" mainly composed of Fe2O3 and Fe3O4, which will form black spots on the surface during subsequent production. Fe2O3 and Fe3O4 are easily soluble in hydrochloric acid. To prevent the formation of dark spots, add 5-10 g/l of sodium chloride to the acid bath.
6. Lubrication
Resin should be used as lubricant. This lubrication is significantly different from phosphating and lubrication (saponification). Drawn steel pipes exhibit the true color of the iron matrix and have the same high smoothness and beautiful appearance as cold-rolled steel pipes.