Welding Specifications for Thermal Pipelines

Feb 28, 2024

Overview of the Standard Process

The welding of thermal pipelines follows a standard process in three stages: bottoming (root pass), interlayer filling, and cover welding. Each stage has specific requirements for procedure, inspection, and defect control, and the quality of every layer determines the final integrity of the pressure joint. The requirements below reflect common industrial practice for carbon and low-alloy steel thermal piping.

1. Bottoming (Root Pass)

The bottoming pass for argon arc welding should be welded from bottom to top. For welding joints that require preheating before welding, the heat treatment personnel should be notified in advance to prepare for preheating, and welding can only be performed after the preheating temperature is reached. When welding, canvas should be used around the welding joint to prevent wind from affecting the quality of the weld. The starting and ending points of spot welding can be ground with an angle grinder to create a slope suitable for the joint, so as to facilitate good fusion and transition of the weld. The entire root layer weld must be evenly penetrated; it must not be welded through, which would cause defects such as weld metal resting on the root and indentation of the root surface. The quality of the bottom welds should be checked in a timely manner and the second layer should be welded promptly to avoid crack formation. For pipes with an outer diameter greater than 194 mm, two-person symmetrical welding should be used for pipe butt joints.

2. Interlayer Filling

After the bottoming pass is completed, if no defects are found, the next layer should be welded immediately. Welding of large-diameter and thick-walled pipes should adopt multilayer and multi-pass welding. The thickness of a single weld bead shall not be greater than the diameter of the welding rod, and the width of a single welding pass shall not exceed four times the diameter of the welding rod. During welding, special attention should be paid to the quality of the joints and the arc closing. When closing the arc, the molten pool should be filled and the joints should be staggered between layers. The quality of welds should be checked layer by layer, and defects found must be dealt with immediately before proceeding.

3. Cover Welding

In order to make the weld appearance smooth, welding rods with a diameter of about 3.2 mm are generally used for the cover pass. The surface of the weld should be complete and even, with a smooth transition to the pipe. The width of the weld should be about 2 mm beyond both sides of the groove, and the reinforcement height of the weld surface shall be 1 to 3 mm. There shall be no cracks, pores, slag inclusions, or spatter on the surface of the weld. There shall be no undercut with a depth greater than 0.5 mm and a total length greater than 10 percent of the total length of the weld.

Quality Control Notes

Preheating and post-weld heat treatment requirements must follow the applicable code and the welding procedure specification for the pipe material. Non-destructive examination such as radiography or ultrasonic testing is normally required on the completed joints according to the service class. All welding consumables should be stored and handled per their classification, and welders must hold qualification for the process and position used.

Frequently Asked Questions

Q: Why is the root pass welded with argon arc welding? A: It provides good root penetration, smooth surface, and no slag, which is favorable for the subsequent cover passes.

Q: Why use multilayer multi-pass welding for thick walls? A: To control heat input, refine the weld structure, and prevent defects such as cracking and excessive distortion.

Q: What are the cover weld acceptance limits? A: Reinforcement 1-3 mm, no cracks or pores, no undercut deeper than 0.5 mm or longer than 10 percent of weld length.

Q: When is preheating required? A: When the welding procedure specification or the pipe material requires it, typically for thicker walls and alloy steels.

Q: How is large-diameter pipe welded? A: Pipe butt joints over 194 mm OD are welded by two welders symmetrically.

Q: What inspection follows welding? A: Layer-by-layer visual inspection plus non-destructive examination such as radiography or ultrasonic testing per the service class.

Planning a thermal pipeline project? Contact us for pipe materials, welding consumables, and specification support.